Projects

Mining site — server room and backup power

Construction of a secure technical room and its power chain, on an isolated site with no reliable public grid.

Reference
KP-2024-008
Sector
Energy and critical infrastructure
Country
Mali
Year
2024
Duration
7 months
An open-pit operation and its substation at nightfall — editorial context image, unrelated to the site of this project.

From source to load, schematic

01Public grid
Normal source. Its availability is measured before it is assumed: it governs everything sized downstream.
02Generator set
Replacement source. It is sized on the measured load balance, never on the sum of the nameplates.
03Automatic transfer
Switches between the two sources. The time it takes is the window the next stage has to cover.
04Main board
Separates what cannot stop from what can wait. That separation is worth more than the capacity added.
05UPS
Covers the generator start-up window on the critical loads alone. Its autonomy follows from that window.
06Critical loads
Server room, security, transmissions. What sits here decides the size of everything upstream of it.
07Sheddable loads
Workshops, comfort, deferrable uses. Shedding them at the right moment avoids paying twice over for a generator.
08Supervision and tests
Grid presence, source state, fuel level, engine hours. What is not measured cannot be attributed to a cause.
Schematic of the chain described above. No equipment, no rating and no real room appears on it.Typical sizing figures, not measured on an installation. The transfer time and the UPS autonomy are those a generator start-up calls for; the load-test interval is the one continuous operation sets.
  1. 01

    The context

    Operations depended on an improvised room: domestic air conditioning, cabling reworked several times, no fire detection, and a supply shared with the workshops. Two production stoppages had already been caused by a power failure, without the exact cause being established for lack of measurement.

  2. 02

    The mission

    Design and build a dedicated technical room, with its cooling, detection, access control and full power chain, then maintain it under contract.

  3. 03

    The architecture

    The public grid and the generator converge on an automatic transfer switch, then on a main board that separates critical from sheddable loads. Critical loads pass through a UPS covering the generator start-up window. Every stage reports to supervision: grid presence, source state, fuel level, engine hours.

  4. 04

    Delivery

    The load balance was measured over four weeks of actual operation rather than estimated from nameplates. It revealed enough growth allowance for two extensions, and ruled out a larger sizing that would have run the generator far below its efficiency range.

  5. 05

    Results

    Operations now have a room with controlled conditions, a replacement source load-tested every month, and measurement that allows an outage to be attributed to its cause. The maintenance contract covers periodic testing and consumable replacement.

  6. 06

    What we take from it

    A measured load balance costs four weeks and changes the sizing. Estimated from nameplates, it almost always leads to oversizing, which degrades both the generator's efficiency and its life expectancy.

Results

4
Weeks of measurement before sizing
12
Load tests per year
7
Months on site

Technologies

  • Perkins
  • Deep Sea Electronics
  • Socomec
  • APC
  • Zabbix

Why some clients are not named here

We design security systems and information systems for organisations whose public exposure is an operational risk. The discretion we apply to their projects is the discretion we will apply to yours. Identities, architectures and contractual documents are shared with an identified organisation as part of a pre-qualification.

Request pre-qualification

Consultations · Pre-qualifications · Partnerships

A comparable requirement?

Site constraints differ from one project to the next, but the questions to settle recur. An initial technical discussion establishes whether the comparison holds.