Mining site — server room and backup power
Construction of a secure technical room and its power chain, on an isolated site with no reliable public grid.
- Weeks of measurement before sizing
- 4
- Load tests per year
- 12
Reference KP-2024-008
Autonomy quoted at full load and autonomy measured on site are two different numbers.
The problem
A UPS is often bought as an energy reserve, with the idea of riding through an outage. That is not its function. Its function is to cover the interval between the loss of the grid and the takeover by another source, and to filter disturbances on the incoming supply.
Two symmetrical mistakes follow from that misunderstanding. Too little autonomy, and equipment stops before the generator starts. Too much, and the organisation ties up a costly, bulky battery bank that has to be cooled and periodically replaced.
Batteries are, besides, the one component of the system that ages with certainty. Their capacity falls with time and with ambient temperature; an installation never tested since commissioning does not know its real autonomy.
Real autonomy and its margin, schematic
Scope
Situations
Requirements
These requirements hold whichever supplier is appointed. Written into a tender, they filter out the responses that will not hold.
Pitfalls
Questions
Enough to cover detection, starting and restoration of the backup source, with a margin for battery ageing. With no backup source, autonomy must allow systems to be shut down cleanly, which is a matter of minutes rather than hours. Longer autonomy is justified only for equipment whose service must be held throughout the outage.
Their life depends mainly on room temperature and on the number of cycles they have been through. A sustained rise of a few degrees above the reference temperature shortens life appreciably. That is why the room is ventilated or cooled, and why battery health is monitored rather than assumed.
They answer different needs and complement each other. The UPS covers the instant, without a break, and conditions the voltage. The generator covers duration, with a starting delay. A critical site needs both; a site whose equipment tolerates a short break may need only the generator.
Often, within the limits allowed by the machine and by the room. Adding them means checking the UPS charging capacity, the floor loading, ventilation and protection of the new bank. Mixing new and old batteries on one string degrades the whole, and is handled by full replacement rather than by topping up.
By an on-load discharge test, run periodically and recorded. It is the only check that measures autonomy rather than declaring it. It is run within an agreed window, with a rollback procedure, because a test is also the moment a weakness reveals itself.
They follow a regulated disposal route and cannot be treated as ordinary waste. The route chosen, the carrier and the traceability of collection are part of the service, and are documented like the installation itself.
Evidence

Construction of a secure technical room and its power chain, on an isolated site with no reliable public grid.
Reference KP-2024-008

Complete overhaul of access control, video surveillance and backup power for a chancery in service.
Reference KP-2022-014
Solutions concerned
Consultations · Pre-qualifications · Partnerships
Describe the site, the dominant constraint and the deadline. We will say what requires a preliminary study and what can be committed directly.
Results
No result.Try a broader word: power, security, network, pre-qualification.
↑↓ Move↵ Open pageEsc CloseAll pages